Free Project Tool

BESS Sizing Calculator & Solution Finder

Quick answer: estimate the battery energy, PCS power range and suitable Zevonexa solution from your load, backup duration, solar, generator and grid conditions. This is a preliminary engineering estimate, not a final system design.

1. Estimate your BESS size






Advanced engineering assumptions

These are adjustable screening assumptions, not Zevonexa performance guarantees. Replace them with verified project and equipment values during engineering.

Basic mode uses load × backup hours with a 20% preliminary margin. Advanced mode is applied only when the checkbox above is selected, and then also adjusts for the user-selected usable DoD and AC delivery efficiency. Final PCS rating, C-rate, SOC window, degradation allowance, redundancy and protection design require project-specific engineering.

2. Find your BESS solution by project problem

3. Compare solutions by outcome, not only specifications

Peak Shaving

Support high-demand periods.

Solar Shifting

Store solar for later use.

Diesel Hybrid

Reduce generator runtime where operating strategy permits.

Backup Power

Support selected critical loads.

4. See how a hybrid microgrid works

SOLAR PV→
EMS / CONTROLLER↔
BESS
↑    ↓
GRID↔
SITE LOAD↔
DIESEL GENSET

The EMS coordinates available sources according to load, grid state, battery limits and the project’s operating strategy.

Engineering Review

5. Send your calculator result to Zevonexa

Your calculated power, energy, PV, generator and backup inputs are automatically copied into this RFQ form after calculation. Complete your contact details and project location so our team can review the result.

Calculate above, then send the project inputs below. Our team can review the preliminary size against the real load profile, grid condition, PV/generator capacity and project stage.



    Worked sizing examples & project guides

    500kW / 1MWh BESS sizing example · 1MW / 2MWh BESS sizing example · Mining BESS sizing · Diesel + BESS sizing · Weak-grid BESS sizing

    Common BESS sizing questions

    How many kWh of battery do I need for a 500kW load?

    Battery energy depends on the load that must actually be supported and the required duration. A 500kW load supported for two hours is 1,000kWh before design margins, efficiency, usable SOC window and project-specific constraints are considered.

    Is kW or kWh more important?

    Both. kW describes power capability; kWh describes stored energy. A project can have enough energy but insufficient power, or enough power but insufficient duration.

    When should I consider 215kWh versus 1MWh?

    Use the required usable energy, power, duty cycle and expansion plan—not catalogue capacity alone. Review the 215kWh BESS and 1MWh BESS, then validate the choice from the actual load profile.

    Read BESS Buyer Guides →   Detailed sizing guide →

    Scroll to Top